News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:10/24/2019 4:30 PM

The following is a brief update on current projects:

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok (CIDC) - Overall Work is 65% complete. Approx. 3 miles of concrete pavement have been placed on south bound lanes of Conroe Park and Pollok Drive.  Scheduled completion: December 2019.

Longmire Road Widening with Wedgwood Extension - Contractor working on underground utilities and storm sewer. Overall 50% of waterline and 50% of storm sewer construction is complete. Temporary pavement widening and the first phase of new pavement construction will begin in Mid-October. Scheduled completion: November 2020

Brass Nail Road and Grace Crossing Extension - Storm sewer construction is 95% complete. New concrete pavement for Grace Crossing Loop has been completed and curb is being poured. Overall project is 85% complete.  Scheduled completion: November 2019.

Robinwood Water Well - Well drilling operation is complete; well development & test pumping has started.  Overall project is 55% complete. Scheduled completion: February 2020.

Proposed Sidewalk Improvements (Semands, Silverdale, & San Jacinto) - 85% complete; Contractor to finish Silverdale and Semands, then move to the Wilson Road and Foster Sidewalks. The Contractor will move back and finish San Jacinto December 2019.  Scheduled completion: September 2019.

Sidewalks - Wilson Road and Foster Drive (federal funding) - Wilson Road Sidewalks - approx. 40% of work is complete.  Scheduled completion December 2019.

Sewer Rehab - Forest Estates and Wroxton - Contractor has completed pre-construction CCTV inspections. Completed 10% of sewer lines rehabilitation.

Overhead to Underground Electrical Conversions (related to Hwy 105 Access Management) - Contractor (A&H) coordinating with power company to inspect transformer pad forms prior to concrete pour.  Scheduled completion: December 2019.

Street Rehab - Milltown Area Phase II - Survey underway. Drainage works started on First Street. Scheduled Completion: June 2020.

SSOI Section -7 Sewer Rehab Ph 2 - Overall rehabilitation work is 40% complete. Scheduled Completion: June 2020.

Central Conroe (New) Treatment Plant-SW Quadrant of Foster & 3rd St. - Council Awarded 8/22/19; working on contracts.

Lift Station Removal- Pebble Glen and Longmire Pointe - Pre-Construction meeting: 10/14/19; project to begin 10/29/19.

3rd Bus Route - Sidewalks & Shelters / Sidewalk - Sgt Ed Holcomb Blvd - Pre-Construction meeting: 10/10/19; Project to begin 10/25/19.

RR Crossing Upgrade - Crighton Road at IH-45 - Council Awarded 9/26/19; working on contracts.

FM 1488 Water System Improvements (Water Well 25) - Council Awarded 9/26/19; working on contracts.

Remove & Replace - Ground Storage Tank Plant 20 (CIDC) - Council Awarded 9/26/19; working on contracts.

Fountain Park Bridges & Trails - Council awarded 10/8/19; working on contracts.

Signal - Sgt. Ed Holcomb at Camelot; Signal - Wally Wilkerson at Conroe Park West (CIDC); Signal - Wally Wilkerson at Pollok (CIDC) - Receive Bids 10/10/19; to be awarded 11/14/19.

Signal Upgrades - City Wide Flashing Yellow Arrows - Receive Bids 10/10/19; to be awarded 10/24/19.

Force Main - Chapel Hill to April Sound - Receive Bids 10/24/19.

Rehab – Live Oak Creek - Receive Bids 11/14/19

Water Line Rehab - Lewis, Roberson, Dallas, & Palestine - Receive Bids 11/21/19

Water Line Rehab - 3rd Street - Receive Bids 11/21/19

Water Line Rehab - Academy Drive and Pozos Area - Receive Bids 11/21/19

Water Line Rehab - Adkins Area - Receive Bids 11/21/19

SUBSTANTIALLY COMPLETE PROJECTS  

  • Camelot Street Extension  
  • Wilson Road Widening & Traffic Signal at Frazier
  • SH105 West Waterline Extension
  • Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3
  • SSOI Section-6 Sanitary Sewer Rehab

 

Return to full list >>