Project Status Report

Post Date:07/26/2019 8:34 AM

The following is a brief update on current projects:

Wilson Road Widening & Traffic Signal at Frazier - Contractor is working on completing final pavement phase and drainage channel

Pollok Drive Conroe Park Drive / Conroe Park Drive & Pollok (CIDC) - Contractor has poured approx. 17,924 sy of pavement. Driveway tie-ins complete and contractor is working on subgrade stabilizations. Scheduled for completion in December 2019.

Longmire Road Widening with Wedgwood Extension – Contractor is working on storm sewer at the north side of the project. Scheduled for completion in November 2020.

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3 - Sewer rehabilitation work substantially complete week of 7/29.

SH105 West Waterline Extension - Contractor has installed 5,000 linear feet of 12" waterline Construction 51% complete; Scheduled completion August 2019

Camelot Street Extension - Construction underway and 38% is completed overall. Scheduled completion September 2019

Brass Nail Road and Grace Crossing Extension – Construction 20% complete; scheduled completion November 2019

Robinwood Water Well – 20% complete; contractor has plugged the old well. The rig has been moved onsite. Scheduled completion February 2020.

Proposed Sidewalk Improvements (Semands, Silverdale & San Jacinto) – 50% complete; Completion September 2019

Sidewalks - Wilson Road and Foster Drive - Pre-Construction Meeting Scheduled for 7/31

Sewer Rehab - Forest Estates and Wroxton - Contract Phase

Overhead to Underground Electrical Conversions (related to Hwy 105 Access Management) – Contract Phase

Street Rehab - Milltown Area Phase II – Contract phase

SSOI Section-7 Sewer Rehab Phase II – Contract phase

Central Conroe (New) Treatment Plant-SW Quadrant of Foster & 3rd St. - Received Bids - 5 Bidders

Lift Station Removal- Pebble Glen and Longmire Pointe - Bidding phase

3rd Bus Route - Sidewalks & Shelters - Bidding phase

Sidewalk - Sgt Ed Holcomb Blvd - Bidding phase

Remove & Replace - Ground Storage Tank Plant 20 (CIDC) - Ad to start 1st week of August; project to begin late Sept. 2019

 

SUBSTANTIALLY COMPLETE PROJECTS  

  • Sewer Rehab – River Pointe Area
  • SSOI Section-6 Sanitary Sewer Rehab
  • Effluent Outfall Structure