Show/Hide

Mayor Toby Powell’s Weekly COVID-19 Updates -  Click Here

Mayor Powell is actively monitoring the COVID-19 pandemic to protect the health and safety of residents, visitors and city employees. It is even more vital at this time that we keep the citizens and businesses apprised of the situation and what our City Staff are doing to safely combat and overcome those obstacles.  Click here for the Mayor's latest updates and to share your comments or questions.

Coronavirus Resources & Updates for Citizens – Click Here

Coronavirus Resources & Updates for Businesses – Click Here

News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:05/29/2020 12:44 PM

The following is a brief update on current projects:

Longmire Road Widening with Wedgwood Waterline Extension - Water: 100% complete and in service. Scheduled completion: November 2020Storm Sewer: 90% completed; Pavement: NB approx 6,800lf; SB approx 1,800lf; Sidewalk: approx 6,800lf complete

Robinwood Water Well - Contractor is waiting on pump motor delivery scheduled late May. Overall project is 85% complete.  Scheduled completion: May 2020

Overhead to Underground Electrical Conversions (related to Hwy 105 Access Management) - A & H is installing pull strings to enable Entergy to pull cable.

SSOI Section -7 Phase 2 - Contractor has completed approximately 15000 lf of sewer rehab and continues work on road repairs and service leads. Scheduled Completion: July 2020

Central Conroe Treatment Plant - SW Quadrant of Foster & 3rd St. - Contractor has completed aeration slabs pour, headworks columns and wall placement, and excavation for clarifiers; bridge deck concrete in place.  Scheduled Completion: March 2022

Lift Station Removal- Pebble Glen and Longmire Point - 8" gravity line along Pebble Glen Drive is complete; the 4" force main along Pebble View Drive complete; lift station packages delivery scheduled for 5/27.

FM 1488 Water System Improvements (Water Well 25) - Pump test complete;tank walls have been installed.  Scheduled completion: March 2021

Remove & Replace - Ground Storage Tank Plant 20 (CIDC) - Contractor has poured wall and dome panels; installing structural steel stress wire.

Fountain Park Bridges & Trails – Pending on boardwalk delivery.  Scheduled Completion: TBD

Signal - Sgt. Ed Holcomb at Camelot; Signal - Wally Wilkerson at Conroe Park West (CIDC); Signal - Wally Wilkerson at Pollok (CIDC) - Foundations have been installed; pending delivery of materials and electrical; pole installed at Pollok.  Scheduled Completion: June 2020

Signal Upgrades - Flashing Yellow Arrows - 16 intersections have been activated.  Completion: May 2020

Force Main - Chapel Hill to April Sound - Contractor has installed 2400 lf; hangers on 105 bridge have been installed; pending electrical submittal review. Completion: July 2020 

Rehab – Live Oak Creek Drainage - Contractor has poured approximately 4500 SY of concrete; working on backfill and site restoration;  Completion: August 2020

Water Line Rehab - Lewis, Roberson, Dallas, & Palestine, 3rd Street, Academy Drive, Pozos, and Adkins Area - Waterline at Academy and Criminal Justice complete; 3rd street area is 99% complete; Scheduled completion: April 2021

Street Rehab - Westview Boulevard & Montgomery Park Boulevard W/sidewalks & waterline - Crew preparing to work on intersections and outside lanes on Montgomery Park Blvd; traffic change scheduled for 6/15; crew has completed connection 12" waterline to Loop portion and has added 400 CY of pavement on Westview and two inlets.  Scheduled completion: September 2020

Drainage Improvements - Bois D'Arc Bend at Walden Road - Project start after utility relocations.

Traffic Signal- Bois D'Arc Bend at Walden Road - Project start after utility relocations.

GLO-CDBG-DR 2016 Flood Grant – Sewer rehab continues; project is 30% complete overall;  Scheduled completion: July 2020

Roadway Extension & Bridge Conroe Industrial Park (CIDC) & Farrel Road; CIDC Utilities (sewer & water) – Contractor installed approximately 1730 lf of 10" sanitary sewer; install approximately 4405 lf of 12" water line; installed approximately 450lf of 12" sanitary sewer; Scheduled Completion: April 2021

Water Plant #26 (McCaleb) – Processing contract documents.

Sewer System Improvements - Carl Barton – Processing contract documents.

Market Street Roadway Extension –  Processing contract documents; pre-construction meeting: 6/4

CIDC Lift Station – Processing contract documents.

Water Plant #26 Access Road – Processing contract documents; pre-construction meeting: 6/3

SUBSTANTIALLY COMPLETE PROJECTS  

  • Street Rehab - Milltown Area Phase II
  • Sidewalk Improvements: Wilson Road and Foster Drive/Federal Funding
  • Sewer Rehab - Forest Estates and Wroxton
  • Sidewalk Improvements: Semands, Silverdale & San Jacinto
  • Wilson Road Widening & Traffic Signal at Frazier
  • 3rd Bus Route – Sidewalks & Shelters/Sidewalk – Sgt Ed Holcomb Blvd