News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:01/24/2020 9:00 AM

The following is a brief update on current projects:

Longmire Road Widening with Wedgwood Extension - Working on temporary widening. Waterline is complete and 75% of storm sewer construction is complete.  Working on temporary pavement widening.  Scheduled completion: November 2020

Brass Nail Road and Grace Crossing Extension - Overall work is 99% complete, pending striping. Expected to open in January.

Robinwood Water Well - Well drilling operation is complete; well development continues & test pumping is complete.  Overall project is 55% complete.  Scheduled completion: February 2020

Proposed Sidewalk Improvements (Semands, Silverdale, & San Jacinto) - 90% complete; Contractor has poured 80% of San Jacinto; Semands and Silverdale are complete.  Scheduled completion: approximately January 2020 

Sidewalks - Wilson Road and Foster Drive (federal funding) - Wilson Road Sidewalks complete. On hold pending bus shelters; contractor to begin Foster area section. Scheduled completion January 2020, pending bus shelter fabrication.

Sewer Rehab - Forest Estates and Wroxton - Contractor has completed pre-construction CCTV inspections. Completed 70% of sewer lines rehabilitation.  Scheduled completion April 2020

Overhead to Underground Electrical Conversions (related to Hwy 105 Access Management) - Contractor (A&H) coordinating with power company, forming transformer pads.  80% of service conduit complete.

Street Rehab - Milltown Area Phase II - Concrete subcontractor work is at 90% and expected to be finished this week; contractor to begin milling week of January 27.  Scheduled Completion: June 2020

SSOI Section -7 Sewer Rehab Ph 2 - Overall rehabilitation work is 40% complete. Scheduled Completion: June 2020

Central Conroe (New) Treatment Plant-SW Quadrant of Foster & 3rd St. - Contractor has begun bores at bridge area and temporary fencing at outfall; submittal review continues; clearing 90% complete.  Scheduled completion: March 2022

Lift Station Removal- Pebble Glen and Longmire Pointe - Reviewing submittals.  Scheduled completion: March 2020

3rd Bus Route - Sidewalks & Shelters / Sidewalk - Sgt Ed Holcomb Blvd - 85% overall completed. Scheduled completion: 2/2020

RR Crossing Upgrade - Crighton Road at IH-45 - Scheduled road closures:  1/18/2020 to 1/19/2020 and 1/25/20 to 1/26/20. 

FM 1488 Water System Improvements (Water Well 25) - Contractor to begin drilling pilot hole; scheduled completion March 2021

Remove & Replace - Ground Storage Tank Plant 20 (CIDC) - Reviewing submittals; scheduled completion: July 2020

Fountain Park Bridges & Trails - Contractor on site.  Scheduled completion March 2020.

Signal - Sgt. Ed Holcomb at Camelot; Signal - Wally Wilkerson at Conroe Park West (CIDC); Signal - Wally Wilkerson at Pollok (CIDC) - Processing submittals.  Scheduled completion: June 2020

Signal Upgrades - City Wide Flashing Yellow Arrows - Processing submittals.  Scheduled completion: April 2020

Force Main - Chapel Hill to April Sound - Pre-Construction Meeting: 1/7/20.  Project to begin mid-January 2020

Rehab – Live Oak Creek  - Pre-Construction Meeting: 1/23/20; Project to begin February 2020

Water Line Rehab - Lewis, Roberson, Dallas, & Palestine - Pre-Construction Meeting: 1/28/20; Project to begin February 2020.

Street Rehab - Westview Boulevard & Montgomery Park Boulevard W/sidewalks & waterline - Council awarded 12/12/19; working on contracts

Drainage Improvements - Bois D'Arc Bend at Walden Road - Council awarded 12/23/19; working on contracts

Traffic Signal- Bois D'Arc Bend at Walden Road - Council awarded 12/23/19; working on contracts

GLO-CDBG-DR 2016 Flood Grant – Receive Bids 1/16/20

Roadway Extension & Bridge Conroe Industrial Park (CIDC) & Farrel Road; CIDC Utilities (sewer & water) – Receive Bids 2/13/20

McCaleb Water Well Construction (Water Well 26) and 1MG Composite EST – Receive Bids 2/20/20

SUBSTANTIALLY COMPLETE PROJECTS   

  • Wilson Road Widening & Traffic Signal at Frazier
  • SSOI Section-6 Sanitary Sewer Rehab
  • Pollok Drive_Conroe Park Drive_(CIDC)