Construction Projects Update

Post Date:04/04/2016 10:02 AM

Roadway & Transportation Projects

Grade Separation (3083): TxDOT held Pre-Construction Meeting for the FM 3083 railroad grade separation over the Union Pacific Railroad. Smith & Co. schedule start date is April 1, 2016

League Line Road (HWY 75-Airport): Concrete paving is done from SH 75 to the Stewart Creek bridge. Paving is scheduled to start next week from FM 1484 headed east. The bridge deck on the creek bridge has been poured. Concrete is scheduled to be
poured on the RR bridge starting next Wednesday. The road is still planned to be complete in September 2016

Candy Cane Park Parking/Driveway: The project is complete

Drennan Road East (Plantation to Frazier): This project is substantially complete. We plan to open in conjunction with the new PD building. Contractor is cleaning the roads and preparing to stripe the road in the next couple of weeks.

Frazier Street Sidewalk (Wilson Rd to Loop 336 N): This project is complete.

 

Construction Projects 

Police Station Construction: Brick and block are approximately 99% complete. They have a few more windows to install. Contractor is painting the interior. Completion date should be May 2016.

SH 242_FM 1488 Lift Station (Construct new lift station on FM 1488 at Carriage Hills Blvd): Poured the top slab (311 7). Preparing wet well for invert and lining. Electrical Control panel installed.

 

Water Projects 

SH 242_FM 1488 Force Main (Construct 10" force main along FM 1488 along south ROW from Carriage Hills Blvd to Johnson Martin Rd.): This project is substantially complete

 

Sanitary Sewer Projects 

N/A

 

Drainage Projects 

N/A

 