Project Status Report

Post Date:01/12/2018 9:00 AM

The following is a brief update on current projects, as of December 29, 2017:

M.P. Clark Roadway: MP Clark: Northbound 8,380' (97%) and Southbound 3578' (43%) completed
Noble Pine: 1217' (100%) Complete
Park Drive: 480' (85% complete) 
Current construction along the East side of Little Egypt Road.
Installation of hike & bike trail is 50% complete
Contractor is working on pavement tie-in at FM 830

Windsor Lakes Lift Station: The contractor is forming and preparing for the baffle wall inside wet well.

Windsor Lakes Force Main: Contractor has installed approximately 8,060 LF of pipe. Boring crew started installing fused pipe 1/11/18. Contractor is clearing the right-of-way/easements and open-Cut installation is in progress along Brass Nail Road.

Traffic Signal: FM 1484 and Technology Parkway: Contractor has completed the foundation for the signal cabinet and underground work is complete.

SH 105/I-45 Sanitary Sewer Rehab Phase 2: Contractor has completed underground work to manhole #6. Major bores complete at Highway 105 and IH-45. Contractor is moving north of Alligator Creek.

Safe School Sidewalks: Contracts with the Mayor for signature. Pre-Construction meeting scheduled for 1/24

League Line Road and Plantation Drive Sidewalks: Contracts due back 1/23.

Wilson Road Widening:  Working on contracts.

Transportation: Hwy 105 Access Management:: Contractor is installing duct bank.

Fire Station No. 7: Working on finalizing the project by the end of January.

Fire Training Facility:  Open House 1/18 