News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:09/07/2018 3:00 PM

The following is a brief update on current projects:

 

Downtown Traffic Signals - 3 Locations: Contractor to remobilize in the field

Safe School Sidewalks:  Contractor has completed 7th Street; project is 94% complete. The contractor has completed Longmire portion of the project. Contractor is pouring curb and gutter along 3rd street; working MLK area and south side of Loop 336.

Wilson Road Widening & Traffic Signal at Frazier:  Contractor has re-opened the road. Utilities: approx. 2050 LF of waterline and approx. 1,200 LF of sanitary sewer installed. 

SSOI Section-6 Sanitary Sewer Rehab:  Pipe bursting approximately 20,600 linear feet complete. Continue working on restoration in other areas. Contractor continues to work on the 8" and 10" pipe bursting. Working on Manholes to be tested.

Grace Crossing Traffic Signal:  All foundations poured.

Grace Crossing Roadway Extension:  100% of the storm is complete and contractor has completed the Fence next to Valero.  Contractor has poured east half that ties in; approximately 420 lf of roadway next to the fence. Contractor has begun water and sewer work.

FM 2854 Water Relocation, Sewer Relocation, and Pipe Bursting:  Contractor has started working on the pipe bursting and has completed 2,500 linear feet and 4 manholes.

Effluent Outfall Structure:  Approximately 2,140 linear feet of pipe has been installed. Dressing up of project is underway and bypass system being installed.

Freedom Boulevard (aka Veterans Memorial Park Drive):  Contractor has placed approximately 80% of the fill and 750 lf of pipe, working at second driveway. Entergy power to be back on by end of Sept.

Signal - S. Loop 336 at Conroe Medical Center Drive:  Award: 9/13/18

SSOI Section 7 - Phase 1:  Award: 9/13/18

WWTP - Fiber Connectivity:  Advertise: 8/19, 8/30, 9/11.  Pre-Bid Meeting: 9/5.  Receive Bids: 9/13

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok (CIDC):  Advertise: 8/26, 9/4, 9/10.  Pre-Bid Meeting: 9/5.  Receive Bids: 9/13

Longmire Road Widening:  Bid Fall 2018 (30-60 days); Gas Line relocation has started.

Sewer Rehab - River Pointe Area:  Bid Fall 2018

Install High Water Gates on TxDOT Roads:  Multiple Use Agreement (MUA) received for all locations

 

SUBSTANTIALLY COMPLETE PROJECTS  

  • Windsor Lakes Lift Station:
  • Windsor Lakes Force Main:
  • SH 105/I-45 Sanitary Sewer Rehab Phase:
  • League Line Road and Plantation Drive:
  • M.P. Clark Roadway:
  • Street Rehab & Asphalt Overlay Project:
  • Traffic Signal: FM 1484 and Technology Parkway:

 

Joint Participation Projects / Inspections Only Projects / In-House Construction Projects      

Chase Run Water Line Extension:  PW in house construction. Council Approved materials 8/23

Transportation: Hwy 105 Access Management:  Contractor is working on the south side driveways and sidewalk. The contractor installing irrigation and power.

 

 

Return to full list >>