The City of Conroe would like to notify the citizens of a possible fraud in the community.  In the last several weeks the City of Conroe Public Works Department has received calls from concerned customers regarding persons visiting their residences, announcing that they are from the City of Conroe, and requesting to test their water. The City of Conroe Public Water system has a Superior rating with the Texas Commission on Environmental Quality (TCEQ).  The TCEQ tests the City water and water quality meets or exceeds all EPA and TCEQ primary drinking water standards. Neither agency recommends further treatment.  For more information click here.

News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:05/17/2019 10:30 AM

The following is a brief update on current projects:

Wilson Road Widening  & Traffic Signal at Frazier - New Traffic Signal is complete.  Three out of five phases of roadway widening are complete. Underground utilities and storm sewers are 95% complete.

Signal - Loop 336 at South Conroe Medical Drive - Traffic Signal installed; Message Board will be set up in anticipation of signal activation.  Signal to be activated by the end of May due to Entergy weather delay.

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok (CIDC) - Temporary traffic control has been implemented. Contractor has poured approx. 4700 sy of pavement.  Working on driveways tie-ins and subgrade stabilizations.  Scheduled for completion in December 2019.

Longmire Road Widening with Wedgwood Extension - Construction to begin in mid May, 2019.

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3 - Sewer rehabilitation work 80% complete.

Sewer Rehab - River Pointe Area - Sewer rehabilitation work 70% complete; contractor working on excavation and restoration.

SH105 West Waterline Extension - Construction underway; Scheduled completion August 2019.

Camelot Street Extension - Construction underway; Scheduled completion August 2019

Brass Nail Road and Grace Crossing Extension - Contracting phase; Construction to begin in June, 2019.

Robinwood Water Well - Construction to begin in June, 2019.

Sidewalks - Wilson Road and Foster Drive - Bidding phase; Construction to begin in June, 2019.

Proposed Sidewalk Improvements - Construction to begin in June, 2019.

Lift Station Removal- Pebble Glen and Longmire Pointe - Bid July 2019; project to begin Sept. 2019.

Decommission Elevated Storage Tank No. 5 - Bidding Phase (Public Works to oversee project).

Street Rehab - Milltown Area Phase II - Bidding phase; Construction to begin in July, 2019.

Central Conroe (New) Treatment Plant-SW Quadrant of Foster & 3rd St. - Bid Phase to begin 5/31/19.

Sewer Rehab - Forest Estates and Wroxton - Bid Phase.

Overhead to Underground Electrical Conversions (related to Hwy 105 Access Management) - Bid Phase.

SSOI Section-7 Sewer Rehab Ph 2 - Bid Phase.

 

SUBSTANTIALLY COMPLETE PROJECTS  

  • WWTP - Fiber Connectivity
  • Downtown Traffic Signals - 3 Locations
  • SSOI Section-6 Sanitary Sewer Rehab
  • Effluent Outfall Structure