Project Status Report

Post Date:04/19/2018 9:00 AM

The following is a brief update on current projects:

M.P. Clark Roadway:
Sidewalk 100 % complete.
MP Clark Main Lane Pavement:
NBL: completed to 8376 LF; 98% (level up remaining at FM 830  tie-in)
SBL: completed to date - 6,700 LF; 77%
Noble Pine & John Burge Park Drive: 100% Complete
Traffic Signal at League Line set to flashing
Windsor Lakes Lift Station: Entergy meter was installed. Lift Station coating complete.
Installing lift station piping.

Windsor Lakes Lift Station: Entergy meter was installed. Lift Station coating complete. Installing lift station piping.

Windsor Lakes Force Main: Approximately 15,500 LF of force main pipe installed. Contractor continues to test line. Contractor is continuing to install bridge pipe.  FM 1488 bore continues this week and completion is expected by next week. Working with ICTX to move fiber optic.

Traffic Signal: FM 1484 and Technology Parkway: Signal to be set to flash on Saturday, April 7 and to be turned on Wednesday, April 11.

SH 105/I-45 Sanitary Sewer Rehab Phase 2: Approx. 3,800' of 24" (75%) sewer and approx. 370' of 12" sewer completed including 24 new manholes. Contractor has installed box culvert through Weisner parking lot, Contractor extending sewer laterals to new trunk line.

Safe School Sidewalks: Contractor has poured approximately 1000 ft from Montgomery Park west. Contractor poured 8 driveways on south 7th street and preparing for pour this week on S. 7th Street.

League Line Road and Plantation Drive Sidewalks: Plantation is complete; contactor has poured 1000 ft on League Line and is continuing to pour this week. 

Wilson Road Widening: Surveying underway.  Utilities being relocated. Reviewing submittals.

Transportation: Hwy 105 Access Management: Contractor has started on driveways on south side.

 