Project Status Report

Post Date:01/28/2019 1:00 PM

The following is a brief update on current projects:

 

Downtown Traffic Signals - Signal Installation is complete. Pending Entergy for power.

Wilson Road Widening  & Traffic Signal at Frazier - The first Phase of five Phases is fully complete and is open to the traffic. The Second Phase of Construction (between Robinhood and Frazier) is 95% Complete.  Underground utilities and storm sewers are 90% complete.

Signal - Loop 336 at South Conroe Medical Drive - Signal installation will begin in February. Scheduled for completion by the end of April, 2019.

SSOI Section 7 - Phase 1 - Approximately 20% of 8,760 linear feet of sanitary sewer rehabilitation is complete.

WWTP - Fiber Connectivity - Approximately 95% of 15,000 linear feet of conduits for communication cables and ground boxes have been installed. Contractor to pull fiber next week.

Conroe Park Drive & Pollok (CIDC) - Construction to begin in February, 2019.

Longmire Road Widening - Construction to begin in late February, 2019.

Sgt. Ed Holcomb Water Line extension - Construction to begin in late January, 2019.

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3 - Construction to begin in February, 2019.

Sewer Rehab - River Pointe Area - Construction to begin in February, 2019.

SH105 West Waterline Extension (Beech to McCaleb) - Construction to begin in February, 2019.

Windsor Lakes - Lift Station Reforestation - Waiting for schedule.

Stewart Creek Mitigation - Planting to begin in late January, 2019.

Camelot Street Extension  - Under bidding phase. Construction to begin in April, 2019

 

SUBSTANTIALLY COMPLETE PROJECTS  

  • SSOI Section-6 Sanitary Sewer Rehab  
  • Freedom Boulevard (aka Veterans Memorial Park Drive)
  • Safe School Sidewalks
  • Grace Crossing Roadway Extension
  • Effluent Outfall Structure

Return to full list >>