Project Status Report

Post Date:10/19/2018 3:00 PM

The following is a brief update on current projects:

 

Downtown Traffic Signals - Contractor road bores for electrical conduit continues.  Forms to be set as weather permits.

Safe School Sidewalks - Project is 98% complete. Contractor is installing handrails and pouring driveways week of October 15th.

Wilson Road Widening & Traffic Signal at Frazier - Utilities: approx. 2710 LF of waterline and approx. 1,200 LF of sanitary sewer installed.  Coordination continues with utilities. Contractor has installed 2 inlets and backfilled Cantrell Detention Pond. Phase 2 is in progress.  3 signal foundations have been poured and cabinet is complete.

SSOI Section-6 Sanitary Sewer Rehab - Pipe bursting approximately 28,000 linear feet complete. Continue working on restoration in other areas. Contractor continues to work on the 8" and 10" pipe bursting. Manhole lining and testing continues.

Grace Crossing Traffic Signal - All signals installed; electrical power pending.  Contractor working on PED controls.

Freedom Boulevard (aka Veterans Memorial Park Drive) - Library area paving and curb is complete.  775 ft of paving completed week of October 15th.  Contractor has stabilized to Crawford Electric driveway; is pouring headwalls and forming retaining wall as weather permits.

Signal - Loop 336 at South Conroe Medical Drive - Pre-Construction Meeting 10/17/18; reviewing submittals.

SSOI Section 7 - Phase 1 - Pre-Construction Meeting 10/17/18; reviewing submittals.

WWTP - Fiber Connectivity - Processing contracts

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok (CIDC) - Bid Award:  10/25/18

Longmire Road Widening - 1st Ad: 10/01/18; 2nd Ad: 10/17/18; Pre-Bid: 10/24/18; 3rd Ad: 10/30/18; Receive Bids 11/1/18; Gas Line relocation continues.

Sgt. Ed Holcomb Water Line extension - 1st Ad: 10/21/18; 2nd Ad: 10/29/18; Pre-Bid: 11/08/18 at 10am; 3rd Ad: 11/9/18; Receive Bids: 11/15/18;

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3 - 1st Ad: 10/21/18; 2nd Ad: 10/29/18; Pre-Bid: 11/08/18 at 2pm; 3rd Ad: 11/9/18; Receive Bids: 11/15/18.

Sewer Rehab - River Pointe Area - 1st Ad: 10/21/18; 2nd Ad: 10/29/18; Pre-Bid: 11/08/18 at 9am; 3rd Ad: 11/9/18; Receive Bids: 11/15/18

 

SUBSTANTIALLY COMPLETE PROJECTS  

  • Windsor Lakes Lift Station
  • FM 2854 Water Relocation, Sewer Relocation, and Pipe Bursting
  • League Line Road and Plantation Drive Sidewalks        
  • Street Rehab & Asphalt Overlay Project                      
  • Grace Crossing Roadway Extension
  • Effluent Outfall Structure
  • Traffic Signal: FM 1484 and Technology Parkway

 