Show/Hide

Normal Trash Pickup for Labor Day Holiday

There will be no change to Waste Management trash services during the upcoming Labor Day holiday, September 3, 2018.  We will continue with normal trash schedule.

News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:08/10/2018 3:00 PM

The following is a brief update on current projects:

 

Windsor Lakes Lift Station (Design: Bleyl):  Working on MUD 95 connection. 36" gravity sewer connection to existing wet well complete.

Windsor Lakes Force Main (Design: Bleyl): 18" Forcemain 100% Complete.
30" Gravity sewer and two manholes completed and tested.

Safe School Sidewalks (Design: Anne):  Contractor has completed 7th Street and MLK Locations; project is 93% complete.

Wilson Road Widening & Traffic Signal at Frazier (Design: Tara/Street & BGE/Signal):  Road scheduled to be complete 8/20:  - Contractor to pour gub and gutter at the first 2 driveways.  Utilities: approx. 1,100 LF of waterline and approx. 1,200 LF of sanitary sewer installed.

SSOI Section-6 Sanitary Sewer Rehab (Design: Tara/Rafael):  Pre-TV on Section 6 is approximately 98% complete; Pipe bursting approximately 8,400 linear feet complete. Continue working on restoration in other areas. Contractor has begun the 8" and 10" pipe bursting. Contractor is working around Hauke Alternative school.

Grace Crossing Traffic Signal (Design: Kimley-Horn):  TXDOT Permit approved.  Two mast arm foundations complete.

Grace Crossing Roadway Extension (Design: Kimley-Horn):  95% of the storm is complete and contractor has completed the Fence next to Valero.

FM 2854 Water Relocation, Sewer Relocation, and Pipe Bursting (Design: Kimley-Horn):  Supplies to be delivered in the filed 8/20, contractor to start pipe bursting on 8/20.

Effluent Outfall Structure (Design: Carollo):  Outfall structure has been installed and tied into the pipe.  Contractor has poured 4th encasement. Approximately 1,900 linear feet of pipe has been installed.

Freedom Boulevard (aka Veterans Memorial Park Drive) (Design: Bleyl):  Contractor has placed approximately 80% of the fill. Box Culvert to be delivered next week. Entergy is moving the pole/utilities.

Signal – S. Loop 336 at Conroe Medical Center Drive (Design: Kimley-Horn): Advertise: 7/29, 8/6, 8/14. Pre-Bid Meeting: 8/8  Receive bids: 8/16.

SSOI Section 7 – Phase 1: Advertise: 8/5, 8/9, 8/21. Pre-Bid Meeting: 8/16. Receive bids: 8/23.

Longmire Road Widening (Design: Bleyl):  Bid Fall 2018 (30-60 days) Gas Line relocation has started.

Sewer Rehab - River Pointe Area (Design: BGE): Bid Fall 2018.

Pollok Drive, Conroe Park Drive, Conroe Park Drive & Pollok (CIDC:  Start Advertising 8/19.

Install High Water Gates on TxDOT Roads: Multiple Use Agreement (MUA) received for all locations.

Transportation: Hwy 105 Access Management:  Contractor is working on the south side driveways and sidewalk. The contractor installing irrigation and power.

 

SUBSTANTIALLY COMPLETE

 

  • SH 105/I-45 Sanitary Sewer Rehab Phase 2: Sewer installation 100% complete and two lift stations taken offline.
  • League Line Road and Plantation Drive Sidewalks
  • M.P. Clark Roadway
  • Street Rehab & Asphalt Overlay Project:Mobilization for additional overlay on 1st St to begin."
  • Traffic Signal: FM 1484 and Technology Parkway
  • Splash Pad - MLK
  • Public Works Service Center