News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:05/17/2019 10:30 AM

The following is a brief update on current projects:

Wilson Road Widening  & Traffic Signal at Frazier - New Traffic Signal is complete.  Three out of five phases of roadway widening are complete. Underground utilities and storm sewers are 95% complete.

Signal - Loop 336 at South Conroe Medical Drive - Traffic Signal installed; Message Board will be set up in anticipation of signal activation.  Signal to be activated by the end of May due to Entergy weather delay.

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok (CIDC) - Temporary traffic control has been implemented. Contractor has poured approx. 4700 sy of pavement.  Working on driveways tie-ins and subgrade stabilizations.  Scheduled for completion in December 2019.

Longmire Road Widening with Wedgwood Extension - Construction to begin in mid May, 2019.

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3 - Sewer rehabilitation work 80% complete.

Sewer Rehab - River Pointe Area - Sewer rehabilitation work 70% complete; contractor working on excavation and restoration.

SH105 West Waterline Extension - Construction underway; Scheduled completion August 2019.

Camelot Street Extension - Construction underway; Scheduled completion August 2019

Brass Nail Road and Grace Crossing Extension - Contracting phase; Construction to begin in June, 2019.

Robinwood Water Well - Construction to begin in June, 2019.

Sidewalks - Wilson Road and Foster Drive - Bidding phase; Construction to begin in June, 2019.

Proposed Sidewalk Improvements - Construction to begin in June, 2019.

Lift Station Removal- Pebble Glen and Longmire Pointe - Bid July 2019; project to begin Sept. 2019.

Decommission Elevated Storage Tank No. 5 - Bidding Phase (Public Works to oversee project).

Street Rehab - Milltown Area Phase II - Bidding phase; Construction to begin in July, 2019.

Central Conroe (New) Treatment Plant-SW Quadrant of Foster & 3rd St. - Bid Phase to begin 5/31/19.

Sewer Rehab - Forest Estates and Wroxton - Bid Phase.

Overhead to Underground Electrical Conversions (related to Hwy 105 Access Management) - Bid Phase.

SSOI Section-7 Sewer Rehab Ph 2 - Bid Phase.

 

SUBSTANTIALLY COMPLETE PROJECTS  

  • WWTP - Fiber Connectivity
  • Downtown Traffic Signals - 3 Locations
  • SSOI Section-6 Sanitary Sewer Rehab
  • Effluent Outfall Structure