Show/Hide

Please be advised that the second Council Meeting in February will take place February 25th at 9:30am and not as previously scheduled for February 27 and 28, 2019.

News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:02/22/2019 1:00 PM

The following is a brief update on current projects:

Wilson Road Widening  & Traffic Signal at Frazier: The first Phase of five Phases is fully complete and is open to the traffic. The Second Phase of Construction (between Robinhood and Frazier) is 95% Complete.  Underground utilities and storm sewers are 90% complete.

Signal - Loop 336 at South Conroe Medical Drive:  Signal installation will begin once signal poles are received. Scheduled for completion by the end of April, 2019.

SSOI Section 7 - Phase 1:  Approximately 50% of 8,760 linear feet of sanitary sewer rehabilitation is complete.

WWTP - Fiber Connectivity :  Approximately 95% of 15,000 linear feet of conduits for communication cables and ground boxes have been installed. Contractor beginning to run fiber optic cable.

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok: Construction to begin in February, 2019.

Longmire Road Widening with Wedgwood Extension:  Construction to begin once utility conflicts have been resolved.

Sgt. Ed Holcomb Water Line extension:  Approximately 1300 lf has been installed.

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3:  Pipe bursting in progress.

Sewer Rehab - River Pointe Area:  Pre-TV continues.

SH105 West Waterline Extension:  Construction to begin in April, 2019.

Camelot Street Extension:  Under bidding phase.  Construction to begin in April, 2019.

 SUBSTANTIALLY COMPLETE PROJECTS  

  • Windsor Lakes - Lift Station Reforestation  
  • Stewart Creek Mitigation
  • Downtown Traffic Signals - 3 Locations
  • SSOI Section-6 Sanitary Sewer Rehab 
  • Grace Crossing Roadway Extension
  • Effluent Outfall Structure