Show/Hide

Christmas Movie in the Park rescheduled to December 14, 2018, 6:00pm due to rain in the forecast.


News

Print
Press Enter to show all options, press Tab go to next option

Project Status Report

Post Date:12/03/2018 3:00 PM

The following is a brief update on current projects:

 

Downtown Traffic Signals - All signal poles are up, Pedestals poles are in the process of being installed. Working on power with Entergy.

Wilson Road Widening & Traffic Signal at Frazier - Utilities: Waterline is complete and approx. 1,200 LF of sanitary sewer installed.
Subgrade stabilization for Phase 2 continues; continue to pour slope paving behind old Buckalew site. West portion of utilities are operational.

SSOI Section-6 Sanitary Sewer Rehab - Pipe bursting approximately 32,000 linear feet complete. Continue working on restoration in other areas. Contractor continues to work on the 8" and 10" pipe bursting. Manhole lining and testing continues as weather permits.

Grace Crossing Traffic Signal - Contractor is working on striping today and the signal will be turned on today.

Freedom Boulevard (aka Veterans Memorial Park Drive) - Library area paving and curb is complete.  775 ft. of paving completed.  Contractor is pouring sidewalks. The contractor is stabilizing between is FM 2854 and Spirit of Texas. Traffic is swapping out today.   

Signal - Loop 336 at South Conroe Medical Drive - Submittals approved. Materials have been ordered, working on the power.

SSOI Section 7 - Phase 1 - Pre-Construction Meeting 10/17/18. Submittals approved. Pre-TV continues.

WWTP - Fiber Connectivity - Submittals review continues. UIR permit approved. 1,000 linear foot of conduit has been installed.

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok (CIDC) - Processing Contracts

Longmire Road Widening - 1st Ad: 10/01/18; 2nd Ad: 10/17/18; Pre-Bid: 10/24/18; 3rd Ad: 10/30/18; Receive Bids 11/1/18; Gas Line relocation continues.

Sgt. Ed Holcomb Water Line extension - 1st Ad: 10/21/18; 2nd Ad: 10/29/18; Pre-Bid: 11/08/18 at 10am; 3rd Ad: 11/9/18; Receive Bids: 11/15/18;

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3 - 1st Ad: 10/21/18; 2nd Ad: 10/29/18; Pre-Bid: 11/08/18 at 2pm; 3rd Ad: 11/9/18; Receive Bids: 11/15/18.

Sewer Rehab - River Pointe Area - 1st Ad: 10/21/18; 2nd Ad: 10/29/18; Pre-Bid: 11/08/18 at 9am; 3rd Ad: 11/9/18; Receive Bids: 11/15/18

 SUBSTANTIALLY COMPLETE PROJECTS  

  • Windsor Lakes Lift Station
  • FM 2854 Water Relocation, Sewer Relocation, and Pipe Bursting
  • League Line Road and Plantation Drive Sidewalks        
  • Street Rehab & Asphalt Overlay Project                      
  • Grace Crossing Roadway Extension
  • Effluent Outfall Structure
  • Traffic Signal: FM 1484 and Technology Parkway
  • Safe School Sidewalks