Project Status Report

Post Date:02/22/2019 1:00 PM

The following is a brief update on current projects:

Wilson Road Widening  & Traffic Signal at Frazier: The first Phase of five Phases is fully complete and is open to the traffic. The Second Phase of Construction (between Robinhood and Frazier) is 95% Complete.  Underground utilities and storm sewers are 90% complete.

Signal - Loop 336 at South Conroe Medical Drive:  Signal installation will begin once signal poles are received. Scheduled for completion by the end of April, 2019.

SSOI Section 7 - Phase 1:  Approximately 50% of 8,760 linear feet of sanitary sewer rehabilitation is complete.

WWTP - Fiber Connectivity :  Approximately 95% of 15,000 linear feet of conduits for communication cables and ground boxes have been installed. Contractor beginning to run fiber optic cable.

Pollok Drive_Conroe Park Drive_Conroe Park Drive & Pollok: Construction to begin in February, 2019.

Longmire Road Widening with Wedgwood Extension:  Construction to begin once utility conflicts have been resolved.

Sgt. Ed Holcomb Water Line extension:  Approximately 1300 lf has been installed.

Sewer Rehab - SH 105/IH45 Sanitary Sewer Phase 3:  Pipe bursting in progress.

Sewer Rehab - River Pointe Area:  Pre-TV continues.

SH105 West Waterline Extension:  Construction to begin in April, 2019.

Camelot Street Extension:  Under bidding phase.  Construction to begin in April, 2019.

 SUBSTANTIALLY COMPLETE PROJECTS  

  • Windsor Lakes - Lift Station Reforestation  
  • Stewart Creek Mitigation
  • Downtown Traffic Signals - 3 Locations
  • SSOI Section-6 Sanitary Sewer Rehab 
  • Grace Crossing Roadway Extension
  • Effluent Outfall Structure

 